![]() |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
The problem with the usual way of constructing a project estimate at completion (EAC) is that adding the estimates for all work breakdown structure (WBS) components does not produce the most likely cost of the entire project. In fact, a recent article emphasized the folly of adding up single-point most likely estimates in its title!2 A cost risk analysis provides a more accurate, realistic and honest estimates of project costs. Why Conduct a Project Cost Risk Analysis? A risk analysis can determine what is the most likely cost for the total project. In addition, it can compute the contingency needed to provide the project explicitly with different measures of protection against cost overruns. It can also provide the project manager with a list of the most risky WBS elements leading to better risk management strategies. Project Cost Risk Analysis - The Risk Data A cost risk analysis starts with the WBS. The next step is to collect data on the extreme optimistic and pessimistic ranges of cost for each of the risky elements. The data collection is the most important phase of a cost risk analysis, and the most difficult. It involves interviewing the team leaders about the risks they see in their own areas of expertise and responsibility. It helps to use a case study to illustrate these points. The low, most likely and high ranges for each element of a simple construction project shows the results of the interviews (see Table 1). Table 1
Ranges for Risk Analysis WBS Category Value for EAC Low Most Likely High ($ thousands) Project Design 1,500 1,400 1,500 3,000 Equipment 5,000 4,750 5,000 6,500 Foundation, Structure 7,000 6,700 7,200 9,500 Piping, Elect. HVAC 1,000 800 1,000 1,600 Labor 4,700 4,700 5,000 6,700 Indirects 6,000 5,650 6,000 8,200 __________ __________ 25,200 25,700 (Notice that two of the EAC estimates are not actually the most likely costs for their WBS category. This can happen and is important in conducting an accurate risk analysis.) After developing the 3-point range estimates, the next step is to choose a probability distribution for each element. Often a triangular distribution is used. An example is shown in Figure 1, below. Figure 1
This triangular distribution implies a 75% likelihood of overrunning the $1 million estimate for this element. Also, the average cost of a triangular distribution is found by the equation (low + most likely + high) / 3 which in this case is $3,400 / 3 = $1,133. So, an overrun of $133 on average can be expected for this component alone without further risk management. This example is not extreme. In many cases the worst case scenario implies overruns of 200% -- 400%, e.g. if a test fails and the component has to be redesigned or reprocured and retested.
The Cost Risk Simulation - Results for Project Management Figure 2
The most likely cost is a little over $28.4 million. The results reveal the need for a 13% contingency just to accommodate the median cost. And there is a 50% likelihood of overrunning the median. The cumulative likelihood estimate developed from the frequency distribution shown in Figure 2, provides the contingency levels for each degree of overrun risk. Table 2
The table shows that the EAC of $25.2 million is not on the radar screen. Also, the contingency can be calculated and interpreted correctly using this table. For instance, a conservative company might require a contingency, which leaves only 20% likelihood of overrun as shown in the box. The contingency would be $29.337 million or 16.4% of the EAC. Further Steps in a Cost Risk Analysis Also, a cost risk can provide information about the location of risk in the project. In a 6-element WBS, the priorities for the project manager can be identified by inspection. If there are hundreds of WBS elements, this can pose serious problems for risk management. Cost risk assumptions can be used to reveal the highest-risk areas for risk management. The chart below shows the highest risk elements in red, the moderate risk elements in yellow and the low risk element in green. Table 3
Finally, the contingency or "risk dollars" can be allocated to the WBS elements, which cause most of the overall project cost risk. Such allocation, if desired, is affected by any correlation that might exist. Summary To get a more accurate picture of the costs of a project, a cost risk should be conducted. The cost contingency that results is easy to interpret. If the initial results from the cost risk implies project costs that are not what the customer or owner desires, risk management can be conducted to reduce the risk in the project cost. The risk analysis can indicate where in the project cost risk is greatest. 1 © 1999 by David Hulett. The author is Principal, Hulett & Associates, Project Management Consultants of
2 Steve Book, "Do Not Sum 'Most Likely' Cost Estimates" presented at the Space Systems Cost 3 Final Report of the USAF Risk Analysis Study Team, August, 1971 4 Paul Garvey, "A General Analytic Approach to a System Cost Uncertainty Analysis," in 5 Final Report of the USAF Risk Analysis Study Tea
For more information: David T. Hulett, Ph.D. © 2005 Hulett & Associates LLC |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||